Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73354 REL 27: 2007-401-00 EXP KELT RECONDITIONING/REPRODUCTIVE SUCCESS 2019
Project Number:
Title:
Kelt Reconditioning and Reproductive Success Evaluation Research
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Snake Lower 100.00%
Contract Number:
73354 REL 27
Contract Title:
2007-401-00 EXP KELT RECONDITIONING/REPRODUCTIVE SUCCESS 2019
Contract Continuation:
Previous: Next:
73354 REL 7: 2007-401-00 EXP BIOP KELT RECONDITION/REPRODUCTIVE SUCCESS 2018
  • 73354 REL 45: 2007-401-00 EXP KELT RECONDITIONING/REPRODUCTIVE SUCCESS 2020
Contract Status:
Closed
Contract Description:
The Kelt Reconditioning and Reproductive Success Evaluation Project is a research, monitoring, and evaluation (RM&E) uncertainties category project funded through the Columbia Basin Fish Accords.  The objectives are to evaluate methodologies to produce viable artificially reconditioned repeat steelhead spawners and to determine the productivity of repeat spawners.  Work occurs in both the Yakima and Snake river basins.  We focus on collecting steelhead kelts at juvenile bypass facilities in Prosser and Lower Granite dams, and additionally some fish are collected at Dworshak National Fish Hatchery.  These kelts were reconditioned (given prophylactic treatments and fed a specially formulated diet) at Prosser and Dworshak National Fish Hatcheries.  Survival of long-term reconditioned kelts has been 42% (17 years) for Yakima River at Prosser Hatchery and at Dworshak Hatchery 21% (5 years) for hatchery origin fish, 33% (6 years; 46% over the last 4 years) for mixed stock collections at Lower Granite Dam, and in previous years Fish Creek and the South Fork Clearwater River.  

Experiments are conducted to better understand the survival and rematuration process and investigate optimum management scenarios for reconditioned fish.
Account Type(s):
Expense
Contract Start Date:
07/01/2019
Contract End Date:
06/30/2020
Current Contract Value:
$1,651,857
Expenditures:
$1,651,857

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Minda Donnelly Department of Energy - IGE No Interested Party minda.donnelly@doe.gov (702) 295-0874
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Christine Golightly Columbia River Inter-Tribal Fish Commission (CRITFC) No Interested Party golc@critfc.org (503) 731-1288
Jen Graham Confederated Tribes of Warm Springs No Interested Party jennifer.graham@ctwsbnr.org (541) 553-3585
Douglas Hatch Columbia River Inter-Tribal Fish Commission (CRITFC) Yes Contract Manager hatd@critfc.org (503) 731-1263
Tracy Hauser Bonneville Power Administration Yes COR tlhauser@bpa.gov (503) 230-4296
Kristen Jule Bonneville Power Administration No Interested Party krjule@bpa.gov (503) 230-3588
Maureen Kavanagh Bonneville Power Administration Yes Interested Party makavanagh@bpa.gov (503) 230-4272
Crystal Miller Department of Energy - IGE No Interested Party crystal.miller@doe.gov (702) 295-0779
Zachary Penney Columbia River Inter-Tribal Fish Commission (CRITFC) No Supervisor zpenney@critfc.org (503) 731-1301
Andrew Pierce Columbia River Inter-Tribal Fish Commission (CRITFC) No Technical Contact apierce@uidaho.edu (808) 265-4547
Chris Roe Columbia River Inter-Tribal Fish Commission (CRITFC) No Administrative Contact chris.roe@critfc.org (503) 731-1274
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494
Emily Wiegert Department of Energy - IGE No Interested Party emily.wiegert@doe.gov (123) 456-7890
Jae Woo Department of Energy - IGE No Interested Party jae.woo@doe.gov (702) 295-0874
Elham Zolmajd-Haghighi Bonneville Power Administration Yes Contracting Officer ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Coverage Documents A: 165. Produce Environmental compliance document for kelt activities 06/30/2020 06/29/2020
Collection of kelt steelhead B: 66. Collect, hold, and transport kelt steelhead for experiments 06/30/2020 06/29/2020
Biological data collection on adult steelhead C: 157. Collect biological data and tissue for genotyping from adult steelhead 06/30/2020 06/29/2020
PIT tagging adult steelhead D: 158. PIT tag adult steelhead at collection sites 06/30/2020 06/29/2020
Recondition & Rear steelhead kelts E: 176. Recondition kelt steelhead for long term treatments 06/30/2020 06/29/2020
Collection of biological data from reared fish F: 157. Collect survival, condition, and rematuration data on reared kelt steelhead 06/30/2020 06/29/2020
Data analysis G: 162. Analyze kelt steelhead post rearing data 06/30/2020 06/29/2020
Generate Genotypic data H: 157. Genotype tissue samples from adult and kelt steelhead, and from resident O. mykiss 06/30/2020 06/29/2020
Conduct genetic analysis I: 162. Conduct parentage assignments, and stock identification from genetic data 06/30/2020 06/29/2020
Implement Snake River Kelt Reconditioning Research Plan J: 157. Implement Snake River Kelt Reconditioning Plan 06/30/2020 06/29/2020
Compete the 3 step process for a Snake River Kelt Reconditioning Facility K: 196. Complete 3 Step Process for a Snake River Kelt Reconditioning Facility 06/30/2020 06/29/2020
Produce Presentations L: 161. Present findings with presentations 06/30/2020 06/29/2020
Work toward submitting a peer-reviewed journal article M: 183. Work toward submitting a peer-reviewed journal article 06/30/2020 06/29/2020
Attach Hatchery Reconditioning Plan N: 174. Hatchery Reconditiong Plan 06/30/2020 06/29/2020
Effective implementation management and timely contract administration O: 119. Manage project and subcontracts for kelt project 06/30/2020 06/29/2020
Completed Annual Report P: 132. Submit 2019 Annual Report for January 2019 to December 2019 03/16/2020 03/13/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 183 Produce Journal Article
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 2 instances of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 196 Council Step Process
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 183 Produce Journal Article
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce Environmental compliance document for kelt activities 07/01/2019
B 66 Collect, hold, and transport kelt steelhead for experiments 02/19/2019
C 157 Collect biological data and tissue for genotyping from adult steelhead 02/19/2019
D 158 PIT tag adult steelhead at collection sites 02/19/2019
E 176 Recondition kelt steelhead for long term treatments 02/19/2019
F 157 Collect survival, condition, and rematuration data on reared kelt steelhead
G 162 Analyze kelt steelhead post rearing data 07/01/2019
H 157 Genotype tissue samples from adult and kelt steelhead, and from resident O. mykiss 02/19/2019
I 162 Conduct parentage assignments, and stock identification from genetic data 07/01/2019
J 157 Implement Snake River Kelt Reconditioning Plan 02/19/2019
K 196 Complete 3 Step Process for a Snake River Kelt Reconditioning Facility
L 161 Present findings with presentations 07/01/2019
M 183 Work toward submitting a peer-reviewed journal article 07/01/2019
N 174 Hatchery Reconditiong Plan 07/01/2019
O 119 Manage project and subcontracts for kelt project 07/01/2019
P 132 Submit 2019 Annual Report for January 2019 to December 2019 07/01/2019
Q 202 BiOp RPA Report for CY 2019
R 185 Periodic Status Reports for BPA 07/01/2019